DOT Updates – Niantic Drawbridge construction

DOT Project 44-154

07/01/2020 CT DOT’s four week look ahead schedule

The schedule for the Rt 156/Niantic River Bridge Project is as follows:

  • Alternating 1-way traffic Mo-Fr 6am-2:30pm with no night work from now until at least July 24th.
  • There will be no road work on this Friday July 3rd.
  • Millstone Rd in Waterford will be closed starting on July 14th for the foreseeable future.

06/17/2020 CT DOT’s four week look ahead schedule

The schedule for the Rt 156/Niantic River Bridge Project is as follows:

  • Alternating 1-way traffic Mo-Fr 6am-2:30pm with no night work from now until at least July 10th

If the public has any questions with regards to this project, they should email the DOT at DOT.Info.NianticRiverBridge@ct.gov

05/29/20 Stair Tower

The stair tower is now back open.
We will need to close the stair tower for one day in about a month to apply a sealer.

05/04/20 Three-week Lookahead Plan

General
Label Piers for Identification 11-May-20 – 12-May-20

JOINT REPAIRS
Chip surface concrete(stairs) 5-May-20 – 22-May-20
Reconstruct Bridge endblock 25-May-20 – 27-May-20
Pier 05 Header and Joint Reconstruction 28-May-20 – 5-Jun-20

SUBCONTRACTORS
ETC Electric install temp power drop to trailer 13-Apr-20 – 15-May-20 25
Blast All begin moving in material 11-May-20 – 28-May-20