03/29/2023 Update
All senior members of the project team will see email messages sent to elproject@gm2inc.com and will answer swiftly.
Display boards showing the Completed Project rendering have been completed and will be delivered to East Lyme town hall this week.
The Project website will be live in two weeks (April 12).
03/09/2023 Update
DOT Project 44-156 – The Route 161/Exit 74 project is set to begin within the week!
At a meeting today, it was described by the Project Managers as a major project similar to the reconstruction/rebuilding of the Pearl Harbor bridge in New Haven. It will be a 4.5 year project beginning the week of March 13th. It will involve lane closures, detours, and impact traffic in the Town.
The first year of the project will be utility work on Route 161 between Industrial Park Rd and Rt 1. The utility work will include the relocation of utility poles, gas lines, and water and sewer lines on Rt 161. Within the next couple of weeks, the Town will begin to see lane closures. The contract allows for one lane closure in each direction between 9 AM and 3 PM during the day. IT WILL HAVE AN IMPACT ON TRAFFIC DURING THOSE HOURS. Also, the magnitude of the work will result in a gravel road surface at times when underground utilities are being relocated. VEHICLE SPEED WILL HAVE TO BE REDUCED EVEN OUTSIDE OF CONSTRUCTION HOURS BECAUSE THE ROAD SURFACE WILL BE DUG UP DURING THE DAY WITH A TEMPORARY SURFACE OUTSIDE OF CONTRUCTION HOURS.
- Beginning the week of March 13th there will be surveyors in the area placing survey stakes and ribbons. It is not anticipated that there will be lane closures while the survey work is being done next week, but it is possible.
- Following the survey work is when the actual work on relocating the utilities will begin. That is when the lane closures are anticipated to begin. The Project Managers have stated their intention is to notify the Town approximately two weeks in advance of the need to close lanes so ample notification can be provided to the public.
Updates will be provided on the Town’s website, local access TV stations, and Town social media pages (Facebook).
The Project Manager is going to provide a shorter version of the presentation given to the Police, Fire, Public Works, and Schools that will provide more complete details on the entire project (See CT DOT Slide Presentation Mar 2023 below). Once received it will be shared with the community on the sites mentioned above. Also, a request was made for a presentation to the community at a date in the near future.
A website specifically for the project is being developed by the Project Managers and the link to it will be on the Town website once it is available (See CT DOT Project website below). Also, large computer-generated pictures of what the finished project will look like are being prepared by the Project Managers. Once they are available, they will be on display on the website and at most Town facilities (Town Hall, Community Center, Police Department).
Once the Project website (See CT DOT Project website below) is available it will allow for individuals to ask questions, submit a claim if their vehicles get damaged as a result of construction debris and view the construction schedule.
Upon completion the finished project is going to be a major improvement for vehicles, pedestrians, and bicycles along Route 161 and for vehicles on I-95. But it is going to take a while to get there. Lots more information to follow.
Further Information
- Slide Presentation Mar 2023
- Site Plan picture (On display in lower corridor of town hall)
- Environmental Assessment Checklist Oct 2019
- Post-Scoping Notice Oct 2019
- Notice of Scoping May, 2019
- Public Informational Meeting Mar, 2017
- CT DOT Project website (Under Construction)